Supplementary date Configuration in Sub Account 7.9

Configure Supplementary Date in SubAccount 7.9


During March While doing day begin in Sub accounts module a message  as 

“ Please Provide Last Working Day In March and First Working Day In April”

Configuration Procedure:


Log in as Supervisor in Sub Account Module

Go to configuration > Select Supplementary Dates > Current Year 2014

( Please refer your Circle Holiday List . Some of the Circle the March 31st is Holiday )
Last Working Day In March : 29/03/2014 (31.3.14 Holiday)
or
Last Working Day In March : 31/03/2014 (31.3.14 Working)

First Working Day In April   : 01/04/2014

Save

Updates:

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Post a Comment

Previous Post Next Post

Most Visited

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Search Content of www.potools.blogspot.com @