Rollout / Migration Activities to be Monitored by Directorate / Circles / Regions / Divisions / CEPT

SI No Action Description Timeline Source of MIS / Report
1. Hardware Readiness Immediate As per the directions of the Directorate.
2. Network Readiness Immediate As per the directions of the Directorate.
3. Completion of requisite training well in advance Well before rollout As per the timelines given by the Directorate.
4. Long pending reconciliation of PO balances and inventories (cash, stamps, etc.) Well before rollout As per the timelines given by the Directorate.
5. Master Data Validation at DO/RO/CO/operative units & administrative offices 09/05/25 onwards, complete by T-10 Circles to monitor. SOP will be communicated.
6. Device Registration Well in advance before T-7 MIS available in the portal. System admins to collect device data from field units.
7. Mobile Number Updation Well in advance before T-7 Monitored via PIS solution MIS. Field units to collect mobile numbers in advance.
8. TOTP Application Installation Well in advance before T-7 Field units instructed in advance. App link provided on the login page.
9. Rollout Readiness Confirmation (via Migration Master Data) T-7 Rollout Application. Field units login to confirm readiness; DO/RO/CO monitor via the app.
10. Role Assignment by CEPT to RDAs (CO/RO RDAs & Divisional Heads) T-10 RDA roles assigned by CEPT.
11. Role Assignment by DO (as per offices/MDW) T-7
12. Role Assignment by Postmasters/Head of Office/SDH (as per MDW) T-5
13. Ensure Day-End by all identified Offices T-3 Monitored by DO/RO/CO.
14. CSI Data Verification (Cash/Stamps/Undelivered Articles/Money Orders/IPOS/Deposit Bags) T-2 Circles confirm data accuracy to CEPT (migration sign-off). Discrepancies shared for reconciliation.
15. Monitor Office Logins & Migration Sign-off Confirmation T-2 Rollout MIS Application.
16. Ensure Rollout Sign-off by All Offices (including RMS) after Functionality Check T-1 Rollout MIS Application.
17. Account Verification by HO & Cash Account Generation On transaction day Consolidated same-day accounting for BOs/SOs/HOs; approved by HO.
18. Cash Account Verification & Approval by PAO On transaction day PAOs confirm Cash Accounts; transmitted to PFMS via integration.

Key Notes:

  • T-X: Refers to days before the rollout (e.g., T-7 = 7 days prior).

  • MDW: Master Data Workflow.

  • CSI: Core System Integration (legacy data).

  • RDA: Role Delegation Authority.

Updates:

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Post a Comment

Previous Post Next Post

Most Visited

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Search Content of www.potools.blogspot.com @