APT 2.0 Readiness for T-3 , T-2 and T-1 activities

Transition to APT 2.0 – Key Phases and Guidelines

Introduction:
A major IT system upgrade is underway with the rollout of APT 2.0. The source material provides a detailed transition plan divided into three critical phases to ensure a smooth migration. Below is a simplified breakdown:

Phase 1: Readiness Confirmation

Objective: Confirm all preparatory work is complete before migration.
Timelines:
  • Administrative Units (Backend): Must be ready by T-7 (7 days before rollout).
  • Operational Units (Frontline): Must be ready by T-3 (3 days before rollout).
Key Tasks:
✔ Employee data verification.
✔ Role definitions finalized.
✔ Device registration completed.
✔ Counter configurations tested.

Purpose: Ensure people and systems are fully prepared.

Phase 2: Migration Sign-Off (T-2)

Focus: Accurate data transfer from IT 1.0 (CSI) to APT 2.0.

Critical Checks:
Verify closing balances of:
  • Cash in hand.
  • Stamp inventory.
  • IPO stock.
Why It Matters:
  • Errors here will corrupt the opening balance in the new system.
  • Data edits require dual approval (field units + higher authorities).

Phase 3: Final Rollout Sign-Off (T-1)

  • Goal: Conduct a dress rehearsal before go-live.
Actions:
  • Test logins for all employees in APT 2.0.
  • Validate treasury module balances (cash/stamps).
Branch Postmasters (BPMs):
  • Complete Day Begin/Day End processes in the IMA app.
  • Back-closure mandatory for Day End.
Important:
  • No actual transactions allowed before rollout day.
  • Ensures a clean opening dataset with no premature entries.
  • Special Instructions for Mail/Money Orders
Station Bag Concept (T-3):
  • Undelivered articles must be closed as station bags and sent to account offices.
  • Ensures backlog items are processed separately in APT 2.0 post-rollout.
Conclusion
  • This step-by-step strategy emphasizes rigorous checks at every stage to minimize errors. Collaboration between administrative and operational teams is crucial for success.
Key Takeaways:
  • Prepare early (Phase 1).
  • Audit data meticulously (Phase 2).
  • Test thoroughly before go-live (Phase 3).
Follow protocols for mail/money orders to avoid confusion.

Updates:

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Post a Comment

Previous Post Next Post

Most Visited

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Search Content of www.potools.blogspot.com @