Schedule of timelines for GDS Compassionate Engagement (CCE) Cycle in APT 2.0

File No. 17-01/2017-GDS
भारत सरकार /Government of India
संचार मंत्रालय/Ministry of Communication
डाक विभाग /Department of Posts
(जीडीएस अनुभाग /GDS Section)

MOST URGENT

डाक भवन, संसद मार्ग
Dak Bhawan, Sansad Marg
नई दिल्ली/New Delhi – 110001.

Dated: 24-08-2026

To

  1. All Chief Postmasters General
  2. The GM CEPT, Mysuru-570010

Subject: Schedule of timelines for GDS Compassionate Engagement (CCE) Cycle in APT 2.0 – reg.

Please refer to Directorate letter No. 17-01/2017-GDS dated 07.01.2026 on the above-mentioned subject.

2. CEPT has informed that the existing GDS Compassionate Engagement cases have been successfully migrated to APT 2.0. A SOP was also shared with all Circles vide this office email dated 12.08.2026 with request to clear the discrepancies in the Compassionate engagement cases migrated from CCE portal IT 1.0 to APT 2.0 by 20.08.2026 for further processing the cases at CCE level. In view of the successful completion of the migration of Compassionate Engagement cases to APT 2.0, the GDS Compassionate Engagement Module is ready for the cases processing by the Divisional CCE w.e.f 01.09.2026.

3. Accordingly, the half-yearly schedule for processing Compassionate Engagement cases in the newly migrated portal, issued vide the ibid letter dated 07.01.2026, has been revised. The revised schedule is enclosed as Annexure-A.

4. All Circles are requested to ensure completion of all pending verification/processing of Compassionate Engagement cases by 31.08.2026 including cases received under one time relaxation scheme. CEPT is requested to complete the pending development activities and undertake adequate testing to ensure smooth, stable and reliable Go-Live of the Portal on the scheduled date.

This issues with the approval of the Competent Authority.

Encl: Annexure -A

भवदीय/Yours faithfully

Digitally signed by
Anand Singh
Date: 24-08-2026
10:23:41

(आनंद सिंह / Anand Singh)
सहायक निदेशक / Assistant Director (GDS)


Annexure-A

(Annexure-A of the letter No. 17-01/2017-GDS dated 24.08.2026)

Sl No. Activities Tentative Timelines for Half-yearly CCE*
1. CCE meeting and approval of the competent authority  
  CCE meeting to be conducted for the consideration of all pending cases. 1st -10 September
  Scrutinize the cases forwarded by the CCE at the RO/CO level by the concerned AD/APMG 11-25 September
  Consideration of the cases by DPS/PMG/CPMG at RO/CO level as the case may be Upto 25 oct
    26 Oct-10 Nov
2. Vacancy updation and processing  
  Vacancy updation by the division 1-10 Nov
  Vacancy approval by Circle 11-15 Nov
  Processing by CEPT 16-18 Nov
3. Final allotment  
  Submission of the post preference by the recommended candidate 19-25 Nov
  Final allotment of the post and issue of PE letter to the recommended candidate by the division 30 Nov-26

 

Updates:

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Post a Comment

Previous Post Next Post

Most Visited

Follow us on WhatsApp, Telegram Channel, Twitter and Facebook for all latest updates

Search Content of www.potools.blogspot.com @